| Our Role in the Project | Main Contractor |
| Nature of the Project | Building & Civil Works |
| Location of the Project | Turkana County, Kenya |
| Client | World Vision |
| Project’s Lead Consultant | World Vision Architects |
| Project’s Architect | World Vision Architects |
| Contract Sum (1996) | KES 4,500,000.00 |
| Contract Sum Adjusted for Inflation (2019) | KES 23,670,000.00 |
| Project Status/Duration | Feb 2001 to Apr 2001 |
| Scope | - Laying an epoxy pipe (1.5 Km)
- Borehole construction & testing
- Construction of a pump house
|