| Our Role in the Project | Main Contractor |
| Nature of the Project | Civil Works |
| Location of the Project | Mumias Kakamega County, Kenya |
| Client | MUMIAS SUGAR COMPANY |
| Project’s Lead Consultant | Booker – Tate |
| Contract Sum (1995) | KES 96,000,000.00 |
| Contract Sum Adjusted for Inflation (2019) | KES 774,060,000.00 |
| Project Status/Duration | Mar 1995 to Dec 1995 |
| Scope | - Construction of a 250 mm thick
concrete paving - Mass excavation. The total square area
was 21,000 m²
|