| Our Role in the Project | DESIGNATED SUB – CONTRACTOR FOR LAXMANBHAI CONSTRUCTION LIMITED |
| Nature of the Project | Building Works |
| Location of the Project | HURLINGHAM – NAIROBI COUNTY, KENYA |
| Main Contractor | Laxmanbhai Construction Limited |
| Client | REMCO LIMITED |
| Project’s Lead Consultant | REMCO LIMITED |
| Contract Sum (1996) | KES 30,000,000.00 |
CONTRACT SUM ADJUSTED FOR INFLATION (AS OF 2019) | KES S 236,670,000.00 |
| Project Status/Duration | May 1996 to Mar 1997 |
| Scope | - Construction of a block of 6, 3 bedroom
apartments - Basement parking with Cabro paving
|