| Our Role in the Project | Designated Sub-Contractor for Laxmanbhai Construction Limited |
| Nature of the Project | Building Works |
| Location of the Project | Webuye, Bungoma County, Kenya |
| Main Contractor | Laxmanbhai Construction Limited |
| Client | Pan African Paper Mills |
| Project Manager | Pan African Paper Mills |
| Project’s Lead Consultant | Pan African Paper Mills |
| Project’s Architect | Pan African Paper Mills |
| Contract Sum (1988) | KES 8,000,000.00 |
| Contract Sum Adjusted for Inflation (2019) | KES 270,290,000.00 |
| Project Status/Duration | June 1988 to December 1988 |
| Scope | - Mass excavation
- RC water intake
- Waterproofing
- Water treatment plant
|