Field Details
Our Role in the Project Designated Sub-Contractor for Laxmanbhai Construction Limited
Nature of the Project Building Works
Location of the Project Muthaiga – Nairobi County, Kenya
Main Contractor Laxmanbhai Construction Limited
Client Mr. & Mrs. Sheikh
Project’s Lead Consultant Denis Lanferna
Project’s Architect Denis Lanferna
Contract Sum (1991) KES 18,000,000.00
Contract Sum Adjusted for Inflation (2019) KES 409,820,000.00
Project Status/Duration June 1991 to March 1994
Scope
  • Construction of a bungalow
  • Building works
  • Electrical works
  • Plumbing works
  • Indoor and outdoor Jacuzzi & Spa
  • Solar heated swimming pool
  • Dark pond
  • Aquarium
  • Acoustic generator room
  • Clay bricked paved yard

Related projects