Field Details
Our Role in the Project Main Contractor
Nature of the Project Building Works
Location of the Project Nairobi County, Kenya
Client Aga Khan University Hospital
Project’s Lead Consultant Peter Thomas Architects
Project’s Architect Peter Thomas Architects
Project’s Quantity Surveyor Barker & Barton (Kenya)
Project Value (2004) KES 14,402,116.00
Project Status/Duration 20 Weeks
Scope
  • Building the library
  • Installing library furniture
  • Teaching block
  • Toilet block
  • Generator house
  • Water fountains