| Our Role in the Project | Main Contractor |
| Nature of the Project | Building Works |
| Location of the Project | Kisumu, Kisumu County, Kenya |
| Client | SWAN CARRIERS LIMITED |
| Project’s Lead Consultant | A.V.Khambatia & Associates |
| Contract Sum (1996) | KES 12,000,000.00 |
| Contract Sum Adjusted for Inflation (2019) | KES 94,670,000.00 |
| Project Status/Duration | Dec 1996 to Apr 1997 |
| Scope | - Construction of a 200 mm thick
concrete parking - Massive earthworks. The total
square area was 25,340 m²
|